Just under 500MW. Three units. The refinery was plated for 80MW but the imagineers at Siemens dropped the ball on the condenser so in the summer you could only get 62MW, and in the winter if you were lucky about 70MW.
Siemens makes crappy steam turbines anyways, and they now service Westinghouse (WH turbines were also 'well made'), AEI, Reyrolle made machines so you can only imagine how well theyre taken care of. The best turbines money can buy are either Toshiba or Hitachi, their service is insane good.